7.2.2 Formal Workplace Inspections
All PCML projects will be inspected / audited on a quarterly basis by the PCML Safety Manager or his / her designate.
Each site inspection will produce a site specific inspection report that will be forwarded and reviewed by each construction manager and superintendent. The site management team must ensure that any corrective action arising from these reports is taken so that the hazard is eliminated or controlled. These completed reports shall be compiled into a quarterly safety report to be forwarded to senior management and the Head Office Occupational Health and Safety Committee for review.
PCML will also conduct an annual internal Certificate of Recognition (COR) Audit as well as schedule an external audit (once every three years) to maintain the company’s COR status and help us measure our progress.