11.2.1 Responsibility
The Project (Site) Management Team and / or Site Safety Coordinator or his / her designate will ensure:
- A pre-construction meeting has been scheduled according to Section 2
- A proper filing system for record keeping will be implemented. The Site Superintendent or his / her designate will ensure record keeping as stated in Section 10 and implement changes for any future revisions.
- Confirm all trades have submitted a copy of their Safety Policy and relative work safety plans (as per contract) to the Safety Group prior to the commencement of any work by that trade.
- All primary contractors have completed and submitted the Contractor Safety Information Form listing all sub-trades retained and / or working under their company complete with relevant supervisor and safety representative information. (Appendix Y)
- All necessary permits, precautions, and safety measures have been addressed and / or in place for the protection of public safety before the commencement of the project.
- The PCML Site Specific Safety Program is constructed, implemented and kept up to date and initiate changes to the program when / where needed as project dictates. Post all safety related documents on the safety bulletin board to ensure ease of access. (Appendix V)
- Proper company and safety signage at a minimum required is posted as well as any additional signage to ensure safety and site specific needs.
- The Weekly Record of Site Safety Activity form (Appendix X) is completed and submitted to the PCML Safety Group in a timely manner.